08-Lane Access Controlled Expressways from Greater Noida to Ballia

  • 08-Lane Access Controlled Expressway starts from Eastern Peripheral Expressway near village Sirsi in Greater Noida passing through Gautambudh Nagar to State Highway no. 34 near Phephana in district Ballia. The project has been developed on DBFO basis on PPP Model. All expenses on the project to be borne by the Concessionaire. No financial assistance/grant/fund is being provided by GoUP.
  • Alignment- 08 Lane Access Controlled 1047 kms. (Approx.)
  • Start Point – Ballia
  • End Point – Gre
  • Traversing Through – Gautam Buddha Nagar, Bulandshahar, Aligarh, Budaun, Kanshiram Nagar, Farrukhabad, Shahjahanpur, Hardoi, Unnao, Raibareily, Pratapgarh, Prayagraj, Sant Ravidas Nagar, Mirzapur, Varanasi, Ghazipur and Ballia.
  • Connecting Links – Link-1 Farrukhabad (19.215 km. approx.), Link-2 Lucknow (90.222 kms. approx.) and Link-3 Mirzapur (13.551 km. approx.) Total = 122.985 kms.
  • Estimated length of the Expressway is approximately 952 km. and that of links is 95 kms. Its estimated cost is approximately Rs. 30,000 crores.
Major Bridges 39
Minor Bridges 199
Culverts 1248
Bridge over Ganga 04
Rail Over Bridges (ROBs) 27
Interchanges 25
Flyover 23
Under passes Vehicular- 187, Pedestrian – 244
  • Land Parcels – Bulandshahar, Kanshiram Nagar, Unnao, Raibareily, Pratapgarh, Prayagraj, Varanasi and Mirzapur.
  • Land Requirement – The land required for acquisition for construction of Ganga Expressway and three Link Expressways is 15120 ha. and for land parcels is 11254 ha.
  • Total notified villages - 1949
  • Total village falling in alignment – 1255